# 2026-06-03 14:05:39
## 303 Mariposa Residence Senior Review
[[conest-senior-review]] for [[303-mariposa-residence]].
### Selling Price
[[pdi-bid-estimating|Bid]]'s proposal base bid \$800,000
Joel messaged [[joshua-komis|Joshua Komis]] to clarify.
### Site Run Adders
previous direction to use 15ft adders for site runs
It would be easier to assume 10ft for all cases
Joel agreed
Mariposa's site runs didn't need adders at all
since we added PVC80 stub-ups.
### Site Low Voltage Duct Bank
We assumed 2in conduit,
but did not note this visibly.
### Solar Feeders
Solar [[feeders-takeoff]] used copper feeder size
based on aluminum size shown in Solar set.
No change necessary.
### Material Pricing
Joel requested pricing for the dimmable receptacles from [[pdi-procurement]].
### Mechanical Connections
B-1, B-2 feeders were parallel runs,
but taken off as 2 counts each.
### Telecom
[[telecom-takeoff]] used Cat5e
which we assumed, but did not note visibly.
### Fire Alarm
[[fire-alarm-takeoff]]
> PCM is supposed to keep Systems from
\$10,000 was my budget
assuming a dozen or so interconnected smokes.
\$26,XXX was the quote
for sprinkler monitoring only
### Closeout
#### Sales Tax
[[pdi-accubid-final-price]] 10.35%
#### Equipment
#### General Expenses
"Just the PM so we only need one trip"
Got rid of APM, Foreman
Approved Labor Plan created by Bid,
approved by (Efren's title)
only 3mil or above
coordination study
\$15,000 up to x
\$25,000 above x