# 2026-06-03 14:05:39
|
|
|
|
## 303 Mariposa Residence Senior Review
|
|
|
|
[[conest-senior-review]] for [[303-mariposa-residence]].
|
|
|
|
### Selling Price
|
|
|
|
[[pdi-bid-estimating|Bid]]'s proposal base bid \$800,000
|
|
|
|
Joel messaged [[joshua-komis|Joshua Komis]] to clarify.
|
|
|
|
### Site Run Adders
|
|
|
|
previous direction to use 15ft adders for site runs
|
|
It would be easier to assume 10ft for all cases
|
|
Joel agreed
|
|
|
|
Mariposa's site runs didn't need adders at all
|
|
since we added PVC80 stub-ups.
|
|
|
|
### Site Low Voltage Duct Bank
|
|
|
|
We assumed 2in conduit,
|
|
but did not note this visibly.
|
|
|
|
### Solar Feeders
|
|
|
|
Solar [[feeders-takeoff]] used copper feeder size
|
|
based on aluminum size shown in Solar set.
|
|
No change necessary.
|
|
|
|
### Material Pricing
|
|
|
|
Joel requested pricing for the dimmable receptacles from [[pdi-procurement]].
|
|
|
|
### Mechanical Connections
|
|
|
|
B-1, B-2 feeders were parallel runs,
|
|
but taken off as 2 counts each.
|
|
|
|
### Telecom
|
|
|
|
[[telecom-takeoff]] used Cat5e
|
|
which we assumed, but did not note visibly.
|
|
|
|
### Fire Alarm
|
|
|
|
[[fire-alarm-takeoff]]
|
|
|
|
> PCM is supposed to keep Systems from
|
|
|
|
\$10,000 was my budget
|
|
assuming a dozen or so interconnected smokes.
|
|
|
|
\$26,XXX was the quote
|
|
for sprinkler monitoring only
|
|
|
|
### Closeout
|
|
|
|
#### Sales Tax
|
|
|
|
[[pdi-accubid-final-price]] 10.35%
|
|
|
|
#### Equipment
|
|
|
|
#### General Expenses
|
|
|
|
"Just the PM so we only need one trip"
|
|
|
|
Got rid of APM, Foreman
|
|
|
|
Approved Labor Plan created by Bid,
|
|
approved by (Efren's title)
|
|
|
|
only 3mil or above
|
|
|
|
coordination study
|
|
\$15,000 up to x
|
|
\$25,000 above x
|