# Telecom
> [!info] Scope
> * Telephone
> * Data
> * Cable TV
> [!important]
> Not to be confused with [[low-voltage-takeoff]].
## Note: Empty Conduit
Where `COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
is specified, `FEEDER CONDUIT AND WIRE`/...
is also acceptable.
## "Site Low Voltage Duct Bank"
1. * `Area` = "2 - Site"
* `Phase` = "Site"
* `System` = "LVD - Site Low Voltage Ductbank"
* `Bid Item` = "1 - Site"
`COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
* Size and quantity per proposal > drawings > assume (4) 4"C
* **Length** = Length measured from MDF to 5ft beyond building footprint
_Garden Style:_ Outside of every building
> [!important] Long-Radius Elbows
> Note requirements for long-radius elbows,
> substitute items as necessary.
### Telecom Vaults
"Quazite Box"
polymer concrete enclosure
1. `TEMPORARY ITEMS`/`Quazite Box ...`
* **Material Price** = 1000.00
* **Labor Hours** = 12.00
* **Sort Code ?** = 200
Alternative
1. `COMMON ASSEMBLIES`/`POLES / EXCAVATION / CORING / UG PULL BX`/`MANHOLES / PULL BOXES / EXCAVATION / CONCRETE`/`QUAZITE UG PULL BOXES`/...
## Backbone Riser
* `Phase` = "Building - BOH ..."
* `System` = "TC - Telecom Backbone"
(2) 4"C or (4) 4"C if not shown
### Horizontal Backbone
1. * `Drawing` = Telecom riser diagram
* `Area` = Area of riser room
`COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
* **Length** = Length measured from MDF to IDF
* Input adder length to reach the level of the IDF (Minimum 15ft).
### Vertical Backbone
1. * `Drawing` = Telecom riser diagram
* `Area` = "Typical - Building All Levels"
`COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
* Delete elbows if unnecessary.
* **Length** = Height between floors (Minimum 15ft)
## Telecom Backboard
As shown on plans, only if not excluded in pro
1. * `Phase` = "Building - BOH ..."
* `System` = "TC - Telecom Backbone"
`COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`... PLYWOOD BACKBOARD`
* **Count** = As shown
## Corridor Conduit (Unit MSDE to IDF)
One Takeoff per Area per level
1. `COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
* **Length** = Average of subfeed lengths * # of Units
* **Count** = # of Units
## Inner Duct
For future use (e.g. fiber)
1. `TEMPORARY ITEMS`/`MaxCell 3" 3 Cell`
* **Material Price** = 450.00/C
* **Labor Hours** = 12.00/C
Alternative
1. `COMMON ASSEMBLIES`/`TELECOM SYSTEMS`/`INNERDUCT`/`... (GP)`
## Devices
As shown on plans.
Ignore scope shared with [[electrical-takeoff|electrical]].
(e.g. floor boxes)
1. `COMMON ASSEMBLIES`/`TELECOM SYSTEMS`/...
* .../`BOH / AMENITY ASSEMBLIES`
* .../`SCREWLESS DECORA COVERS UNITS / BOH`
* .../`ROUGH IN ASSY`
If _system_ is included, take off _both_ rough-in and device assemblies