1.2 KiB
id, title, tags, daily
| id | title | tags | daily |
|---|---|---|---|
| 2026-04-27T12:56:35-0400 | 2026-04-27 12:56:35 | 2026-04-27 |
2026-04-27 12:56:35
Virginia Live! Internal Review
virginia-live-casino-and-hotel
Underfloor power is Reloc. Customer is curious if it would be more cost effective to use MC.
Objective is to discuss closeout mainly: quotes and subs.
FF&E Concern that all fixtures are captured
"add a line for aiming and testing" 1 week (80 hours)
Shift rate "in the past we've paid a little more for night work, but nothing crazy"
$2,500 per day scaffold
Site Services
Ditch witches for most excavation
idea floated to buy equipment rather than rent bobcat wire puller hydraulic bender
Do we own dewatering? pretty sure yes
MV Terminations
No one at PDI can perform MV terms so they must be subbed out
worst case $300k
9 terms $60k
to be quoted by Ops
Testing
primary injection testing
NETA testing
to be quoted by Ops
Rigging
Ops quoted $85k to take one generator off the truck.
to be quoted by Ops
Burden
PTO not included in burden because it is not charged to the job
Admin Housing
Ops paying $4,500 for 6-bed
Composite Cleanup
terms in contract
Permits
to be quoted by Ops