Virginia Live! Internal Review

virginia-live-casino-and-hotel

Underfloor power is Reloc. Customer is curious if it would be more cost effective to use MC.

Objective is to discuss closeout mainly: quotes and subs.

FF&E Concern that all fixtures are captured

"add a line for aiming and testing" 1 week (80 hours)

Shift rate "in the past we've paid a little more for night work, but nothing crazy"

$2,500 per day scaffold

Site Services

Ditch witches for most excavation

idea floated to buy equipment rather than rent bobcat wire puller hydraulic bender

Do we own dewatering? pretty sure yes

MV Terminations

No one at PDI can perform MV terms so they must be subbed out

worst case $300k

9 terms $60k

to be quoted by Ops

Testing

primary injection testing

NETA testing

to be quoted by Ops

Rigging

Ops quoted $85k to take one generator off the truck.

to be quoted by Ops

Burden

PTO not included in burden because it is not charged to the job

Admin Housing

Ops paying $4,500 for 6-bed

Composite Cleanup

terms in contract

Permits

to be quoted by Ops