# 2026-04-27 12:56:35
|
|
|
|
## Virginia Live! Internal Review
|
|
|
|
[[virginia-live-casino-and-hotel]]
|
|
|
|
Underfloor power is Reloc.
|
|
Customer is curious if it would be more cost effective to use MC.
|
|
|
|
Objective is to discuss closeout mainly:
|
|
quotes and subs.
|
|
|
|
FF&E
|
|
Concern that all fixtures are captured
|
|
|
|
"add a line for aiming and testing"
|
|
1 week (80 hours)
|
|
|
|
Shift rate
|
|
"in the past we've paid a little more for night work,
|
|
but nothing crazy"
|
|
|
|
$2,500 per day scaffold
|
|
|
|
### Site Services
|
|
|
|
Ditch witches for most excavation
|
|
|
|
idea floated to buy equipment rather than rent
|
|
bobcat
|
|
wire puller
|
|
hydraulic bender
|
|
|
|
Do we own dewatering?
|
|
pretty sure yes
|
|
|
|
### MV Terminations
|
|
|
|
No one at PDI can perform MV terms
|
|
so they must be subbed out
|
|
|
|
worst case $300k
|
|
|
|
9 terms $60k
|
|
|
|
to be quoted by Ops
|
|
|
|
### Testing
|
|
|
|
primary injection testing
|
|
|
|
NETA testing
|
|
|
|
to be quoted by Ops
|
|
|
|
### Rigging
|
|
|
|
Ops quoted $85k to take one generator off the truck.
|
|
|
|
to be quoted by Ops
|
|
|
|
### Burden
|
|
|
|
PTO not included in burden
|
|
because it is not charged to the job
|
|
|
|
### Admin Housing
|
|
|
|
Ops paying $4,500 for 6-bed
|
|
|
|
### Composite Cleanup
|
|
|
|
terms in contract
|
|
|
|
### Permits
|
|
|
|
to be quoted by Ops
|