## Virginia Live! Internal Review
[[virginia-live-casino-and-hotel]]
Underfloor power is Reloc.
Customer is curious if it would be more cost effective to use MC.
Objective is to discuss closeout mainly:
quotes and subs.
FF&E
Concern that all fixtures are captured
"add a line for aiming and testing"
1 week (80 hours)
Shift rate
"in the past we've paid a little more for night work,
but nothing crazy"
$2,500 per day scaffold
### Site Services
Ditch witches for most excavation
idea floated to buy equipment rather than rent
bobcat
wire puller
hydraulic bender
Do we own dewatering?
pretty sure yes
### MV Terminations
No one at PDI can perform MV terms
so they must be subbed out
worst case $300k
9 terms $60k
to be quoted by Ops
### Testing
primary injection testing
NETA testing
to be quoted by Ops
### Rigging
Ops quoted $85k to take one generator off the truck.
to be quoted by Ops
### Burden
PTO not included in burden
because it is not charged to the job
### Admin Housing
Ops paying $4,500 for 6-bed
### Composite Cleanup
terms in contract
### Permits
to be quoted by Ops