# Pre-Takeoff Research
## Requirement Precedence
In case of conflict:
Requirements of the plans and specs
are superseded by the terms of our proposal,
which are superseded by specific direction from the bid team.
<!--
Where NEC, IBC, and other applicable codes fall in this hierarchy
is subject to some debate.
-->
## Wiring Method Selection
See [[wiring-method-selection]].
## Voltage Drop
Unless explicitly stated in the plans or specs,
conductors are to be sized according to the relevant schedule,
_without respect for voltage drop_.
### Feeders and Unit Subfeeds
<!-- TODO: -->
### Branch Circuits
If voltage drop is to be considered in takeoff,
Use the table provided in the drawings.
If no table is provided, use the following:
| Wire Size | Max Length |
| ---------:| ----------:|
| #12 | 100ft |
| #10 | 200ft |
| #8 | >200ft |
## Wiring Device Selection
Wiring devices and their wall plates are a common target of [[gold-plating]].
* Device grade: commercial < specification
* Minimum rating for general-use receptacles: N5-15R < N5-20R
* Device form-factor: Duplex/toggle < Decora
* Device cover plate material: Plastic < nylon < aluminum < stainless steel
* Device cover plate size: standard < mid-size < oversize "jumbo"
* Device cover plate attachment: Standard < screwless
* Floor box material: Steel < cast iron
* Floor box cover plate material: plastic < brass < aluminum
> [!info] Search Terms Relevant to Wiring Device Selection
> * "Decora"
> [!info] Example Specs Relevant to Wiring Device Selection[^1]
> * 26XXXX - Wiring Devices
> * 26XXXX - Boxes And Covers For Electrical Systems
> * 26XXXX - Lighting Control Devices
> * 26XXXX - Network Lighting Controls
[^1]: Specification section titles and scope may vary greatly between projects.
The examples provided are not an exhaustive list.
## Emergency Systems
1. Find Fire Alarm plans (if present)
2. Locate the following rooms:
* Fire Command Center (FCC)
* Generator Room
* Fire Pump Room
* Elevator Control Rooms
* Elevator Shafts
* Stairwells