# 2026-04-23 18:07:49
|
|
|
|
Follow-up to [[2026-04-23_16-24-49]]:
|
|
|
|
Knowing now that [[pdi-operations|Ops]]'s baseline estimate
|
|
isn't entirely redundant with [[conest|ConEst]]'s,
|
|
I'm less convinced that "detailed takeoff"
|
|
(for lack of a better term[^1])
|
|
could easily be removed from the [[pdi-estimating]] process.
|
|
|
|
[^1]: See [[orthodox-construction-estimating]].
|
|
|
|
Suppose that an ongoing project
|
|
with 1000 feet of #2 CU in its CBOM
|