# Conduit Routing
|
|
|
|
## Shear Walls
|
|
|
|
[[construction-methods#Shear Walls|Shear Walls]]
|
|
|
|
Shear walls, like those around stairwells and elevator shafts,
|
|
may be routed through with special permission.
|
|
## Post-Tensioned Slabs
|
|
|
|
[[construction-methods#Post-Tensioned Slab|Post-Tensioned Slab]]
|
|
|
|
> [!cite] Joel Jansen 2025-08-15, in reference to Belle Meade Plaza (pp.)
|
|
> No affect on takeoff. Routing in slab still possible.
|
|
|
|
> [!cite] Joel Jansen 2025-08-21, in reference to Belle Meade Plaza (pp.)
|
|
> PT slabs do have some affect on takeoff.
|
|
> 3in conduit can not be run in an 11in PT slab.
|
|
|
|
## Pan Deck Slabs
|
|
|
|
[[construction-methods#Pan Deck Slab|Pan Deck Slab]]
|
|
|
|
> [!cite] Joel Jansen 2025-08-15, in reference to Belle Meade Plaza (pp.)
|
|
> Do not route in slab.
|