title: "PDI Accubid Closeout: Quoted Material"
tags:
- occupational/closeout
- type/guide
up: "[[pdi-accubid-closeout]]"
---
# PDI Accubid Closeout: Quoted Material
> [!important]
> Quoted material costs must be ==pre-tax==.
## Fixtures
* **Vendor** <- "PDR - {Quote Type}" (e.g. "PDR - Spec/Equal", "PDR - VE")
* **Quote** <- Per PDI Systems proposal
* **Notes** <- Quote date
> [!tip]
> PDR fixture quotes are usually broken out by area type,
> buy it is not necessary to preserve this breakdown in the estimate.
> Use the sum total cost in a single Quoted Materials line item.
## Switchgear
* **Vendor** <- Per quote (or "PDI BUDGET" if not available)
* **Quote** <- Per quote (or Bid Sheet Budget if not available)
* **Notes** <- Quote Date
## Generator
* **Vendor** <- Per quote (or "PDI BUDGET" if not available)
* **Quote** <- Per quote (or Bid Sheet Budget if not available)
* **Notes** <- Quantity, Size in kW, Quote Date