# PDI Labor Plan
1. Fill out project basics
2. Check that everything is sorted into correct `Phase` and `Area` (Extension: Phase - Area)
3. Move everything in BUILDING FA systems into FA phase
* Create `Phase` = "Fire Alarm"
* Check `System` and `Bid Item`
* Scroll through each and select all line items `FA - ...`
* Set `Phase` = "Fire Alarm"
4. Separate all Phases into their proper corresponding `Labor Factor`
* Scroll through each `Phase`
* Change breakdown of everything in each phase to the proper `Labor Factor`
* Do not move Temp Power (budgets) or site
5. Use the [[accubid|Accubid]] Extension tab to fill out the "Unit Lbr Calc" tab in the labor plan
6. Select extension view "Phase, Sort Code"
7. Open `Phase` "UNIT RESIDENTIAL" and "Building - Corridors"
8. Go into each Sort code to find the count for each unit item
| Code | Description |
| ---- | -------------------- |
| 200 | rough |
| 300 | trim |
| 400 | rough wire and cable |
9. Some items will autofill when you fill out the "Accubid Extension Totals" table on the right
* Anything you make adjustments to, highlight red so it can be reviewed
10. Fill out the "Labor for Concrete Slab/Deck Labor" table on the labor sheet calc tab
* For the floor counts, if there are multiple buildings, add their total level count together
* 2 buildings that each have 10 floors, input 20 for "number of floors - building
* Add any useful description to the naming
* Can change "Other" to something more prevalent on the project
* "pour section rate" refers to the size of each slab that will be poured
* sometimes will be shown on the structural plans
* "Number of days per..." equals "Pour Section Qty" times 4 or 5
11. Check that everything is sorted into correct `Phase` and `Area` (Extension: "Phase - Area")