PDI Accubid Closeout: Subcontractors
occupational/closeout
type/guide
pdi-accubid-closeout

PDI Accubid Closeout: Subcontractors

Important

Subcontractor quotes ==must include tax==.

Clear Markup % for all lines.

Quotes

Include all quotes from BPM. If system is not included in the base bid, set Adjustment % to -100%

TWO WAY COMMUNICATION

  • Vendor <- "PDI SYSTEMS"
  • Quote <- Per PDI Systems proposal
  • Notes <- Quote date

FIRE ALARM

  • Vendor <- "PDI SYSTEMS"
  • Quote <- Per PDI Systems proposal
  • Notes <- Quote date; # hours in quote

Budgets

PDI ENGINEERING COORDINATION STUDIES

Only if not included in switchgear quote.

EXCAVATION

Only if we own primary conduit or Site Low Voltage Duct Bank:

  • Vendor <- "PDI BUDGET"
  • Quote <- $10,000

WIREWAYS | TROUGHS | PULL BOXES

  • Vendor <- "PDI BUDGET"
  • Quote <- $10,000 per building (subject to adjustment)

FIRE STOP

  • Vendor <- "PDI BUDGET"
  • Quote <- $25 per Unit (subject to adjustment)

RIGGING

  • Vendor <- "PDI BUDGET"
  • Quote <- Sum of costs per generator:
    • less than 800kW = $5k each
    • 800kW and larger = $10k each

FUEL

  • Vendor <- "PDI BUDGET"
  • Quote <- ...
    • High Density: $5k
    • High Rise: $10k