## Hilltop Gardens Pre-Takeoff Email
|
|
|
|
%%
|
|
Implementation of [[conest-pre-takeoff-email-template]]
|
|
for [[hilltop-gardens]].
|
|
%%
|
|
|
|
Hello Team,
|
|
|
|
Below is a comprehensive list of means & methods for Hilltop Gardens.
|
|
Please confirm you have received this email and respond with any questions or comments.
|
|
|
|
* **Delivery Method:** Plans & Specs %% Plans & Specs, Design Build, Design Assist, P&S with Approved VE %%
|
|
* **Document Stage:** Permit %% DD, CD, Permit, GMP, Bid, Awarded %%
|
|
* **Drawings Date:** 2025-12-12 %% Date %%
|
|
* **Project Manual Date:** N/A %% Date %%
|
|
* **Proposal Date:** 2026-04-16 %% Date %%
|
|
* **Takeoff Request Stage:** Full Takeoff %% Stage 1, Full takeoff, etc. %%
|
|
|
|
### Project Specification Callouts
|
|
|
|
%% Put page of Drawing or PM after answer %%
|
|
|
|
* Conduit Execution Plans:
|
|
* EMT Fittings: Not specified.
|
|
* Rigid elbows where stubbing up from grade. _---E.0.X.1 "ELECTRICAL NOTES" Note 32_
|
|
* PVC slab-on-grade, below grade only. _---E.0.X.1 "ELECTRICAL NOTES" Note 32_
|
|
%% GRC, coupling specs, etc. %%
|
|
|
|
* Wire: AL 1 AWG and above. _---E.4.X.X "WIRE SCHEDULE KEY NOTE"_
|
|
%% Copper or Aluminum, Acceptable Manufacturers %%
|
|
|
|
* Cable Uses: Devices only, homeruns in conduit. _---E.0.X.1 - "ELECTRICAL NOTES" Note 27_
|
|
%% Branch Homeruns %%
|
|
|
|
* Steel Box Depth: Not specified.
|
|
%% 1-1/2", 2-1/8" %%
|
|
|
|
* Floor Boxes: _---E.0.X.1 "ELECTRICAL NOTES" Notes 53, 54_
|
|
* Box Material: Hubbell B-2529 (stamped steel).
|
|
%% Box: PVC, Sheet metal, Cast iron %%
|
|
* Cover Material: Hubbell S-3725 (brass).
|
|
%% Covers: Brass, Aluminum %%
|
|
|
|
* Wiring Devices: All 20A Toggle/Duplex. _---E.0.X.1 "ELECTRICAL NOTES" Note 45_
|
|
|
|
* Switchboards/Panelboards: %% Acceptable Manufacturers, AL or CU Bussing, Breaker Types (Snap-on, bolt on), ACI Ratings %%
|
|
* Bus Material: Copper. _---E.0.X.1 "ELECTRICAL NOTES" Notes 66(G), 67(G)_
|
|
* Breaker Type:
|
|
* General Panelboards: Bolt-On. _---E.0.X.1 "ELECTRICAL NOTES" Note 66(E)_
|
|
* Unit Load Centers: Plug-In. _---E.0.X.1 "ELECTRICAL NOTES" Note 67(E)_
|
|
* Interrupting Current Ratings: "ALL BREAKERS SHALL BE SERIES RATED AT 22K TO THE MAIN BREAKER.
|
|
MAIN BREAKER AIC RATING IS 65K.
|
|
UNIT APARTMENT PANELBOARD MAIN BREAKER AIC RATING 10K."
|
|
_---E.4.X.1 "RISER NOTES" Note (B)_
|
|
* Unit load center covers to be white _---E.3.X.X "KEY NOTES" Note 6_
|
|
|
|
* Transformers:
|
|
* Winding Material: Not specified.
|
|
* K-Rating: Not specified.
|
|
%% Windings AL or CU, K-rating %%
|
|
|
|
* Generator: N/A.
|
|
%% Acceptable manufacturers, Enclosure Specs, Sound Rating, Remote Tank, Tank Size, Load Banks %%
|
|
|
|
<!--
|
|
### Project Drawing/Detail Callouts
|
|
|
|
* Describe conflicts between drawings / proposal:
|
|
%% "Plans show CU feeders, proposal calls for aluminum", Specification grade devices, etc. %%
|
|
|
|
* Cost drivers in details not shown elsewhere on plans:
|
|
-->
|
|
|
|
### PDI System Execution Plan
|
|
|
|
* Primaries: (2) 4"C install only, conduit furnished by FPL. Wiring excluded. _---Proposal 2026-04-16_
|
|
%% Installation only, (9) 6" PVC %%
|
|
|
|
* Secondaries: PVC with RMC stub-ups. AL wiring.
|
|
%% PVC UG, GRC Stub-ups, AL %%
|
|
|
|
* Feeders: PVC in-slab, below grade; EMT OH. AL over 100A. 2% VD.
|
|
%% PVC UG, EMT OH, AL over 100A, 2% VD %%
|
|
|
|
* Unit Subfeeds: PVC in-slab. AL wiring. 3% VD.
|
|
%% MC OH AL, VD per Chart on E5.01 %%
|
|
|
|
* Units: 20A toggle/duplex, USB rec's, disposals, thermostat wiring.
|
|
%% 15A Decora, Insinkerators, T-stat, Floor Boxes, Shade Control, Doorbells, Dimmer Switches, etc. %%
|
|
|
|
* Telecom:
|
|
* Backbone: (4) 4"C UG, (2) 4"C riser each building.
|
|
* Units: 1"C to each unit. Assuming 28" MSDE's. Excluding homeruns and cabling. Stub-ups each outlet.
|
|
%% 42" MSDE, No Cable Homeruns, (1) 1" Back to IDF, CAT6 with Stub-ups %%
|
|
|
|
* EV Chargers: (12) conduit, wire, equipment. _---E.1.X.1, Proposal 2026-04-16_
|
|
%% (42) Conduit only, (56) Conduit & Wire, (20) Conduit, Wire & Equipment %%
|
|
|
|
* Fire Alarm: PVC in-slab, below grade. 120V smokes in units.
|
|
%% Free-air where allowed by code. EMT Risers. %%
|
|
|
|
* DAS: Sleeving and pathways only.
|
|
%% Conduit only, Per PDI DAS Design %%
|
|
|
|
* Low Voltage: All pathways, conduit, wiring, equipment excluded.
|
|
%% Free-air where allowed by code. Stub-ups to accessible ceilings. %%
|
|
|
|
### Lighting Control
|
|
|
|
* Scope: Per plans. See E.6.X.2 "TYPICAL LOW VOLTAGE LIGHTING CONTROLS".
|
|
%% Code Minimum per Energy Code Assigned, P&S, PDI Design %%
|
|
|
|
* Governing Code: FBC 2023 (IECC 2021)
|
|
|
|
* Area: %% Assign Method to Areas: Line Voltage, Low-Voltage Stand Alone or Centralized System %%
|
|
* BOH: Line voltage.
|
|
* Corridor: Digital standalone.
|
|
* Amenity: Line voltage.
|
|
* Site/Landscape: Line voltage.
|
|
* Garage: Line voltage.
|
|
|
|
### Tasks/Quotes Needed for WBS
|
|
|
|
<!--
|
|
Delete any tasks completed.
|
|
If all necessary tasks are open or completed:
|
|
"No tasks missing."
|
|
-->
|
|
|
|
* Switchgear
|
|
* Fire Alarm
|
|
* Electrical Constructability Review
|
|
* Electrical VDC
|
|
* Coordination Study %% Design Build: Not needed. %%
|
|
* DAS Public Safety Raceway Design
|
|
|
|
<!--
|
|
DAS Public Safety Raceway Design is necessary
|
|
if we own DAS pathways but not the system,
|
|
since if we own the system,
|
|
the raceway design will be included in the Systems quote.
|
|
-->
|
|
|
|
Thank you,
|