# Lightning Protection
## Info
Two Types:
- Protection \$\$\$
- Prevention \$
- ESE (EARLY STREAMER EMISSIONS)
## Estimate Scope
May or may not be included, see proposal on [[bpm|BPM]]
### Subcontractors
Find lightning protection subcontractor quotes on BPM
> [!tip]
> While you have them open, put the quote costs in Accubid.
Search the quotes for direction on downlead counts, total length, and conduit size
> [!example]
> Contractor to furnish 1,980' of 1" PVC conduit and pull string
If no quote is available:
- **Downlead locations** = building corners + additional locations
such that downlead spacing is not greater than 100ft
- Minimum 10 locations for High Rise
- **Total downlead conduit length** = building height * downlead locations
- **Conduit size** = 1-1/4"
### Takeoff
```
Area = "Lightning Protection" // confirm
Phase = "Building - BOH, Storage & Common"
System = "LPT - Lightning Protection"
BidItem = "3 - Building"
```
- Takeoff: `COMMON ASSEMBLIES`/`PDI EMPTY CONDUIT`/`PVC ASSEMBLIES`/`* CONDUIT - PVC40`
- **Length** = total downlead conduit length
- **Count** = downlead locations
- Add item: `ITEM DATABASE`/`BOXES & CABINETS`/`JUNCTION BOXES AND INDUSTRIAL CABINETS`/
`BOXES - HNGD CVR - PAINTED STEEL - NEMA 1`/` 6x 4x 4" BOX HNGD CVR - NEMA 1`