# Risk Oriented Estimating
|
|
|
|
Risk-Oriented Estimating (ROE), is a methodology for [[construction-estimating]] which
|
|
* prioritizes estimating tasks,
|
|
* determines necessary [[estimating-detail]]
|
|
|
|
ROE leans heavily on [[perfect-information]],
|
|
which challenges the natural tendency to shy from uncertainty
|
|
with the reality of the cost of certainty.
|
|
|
|
ROE does not endorse common shortcuts that round up to "cover" uncertainty,
|
|
as these ultimately _increase_ risk by inflating the apparent project cost,
|
|
increasing the probability of loss to a competitor.
|
|
|
|
%%
|
|
## Scratch
|
|
|
|
Bid risk may fit a [Taleb distribution](https://en.wikipedia.org/wiki/Taleb_distribution).
|
|
|
|
Actuarial Science
|
|
|
|
Estimating as risk mitigation,
|
|
resources allocated by Return on Mitigation (RoM)
|
|
|
|
%%
|
|
|
|
## Prioritizing Tasks
|
|
|
|
ROE prioritizes estimating tasks by their contribution to _cost certainty_.
|
|
|
|
## Determining Necessary Detail
|
|
|
|
ROE determines the appropriate level of [[estimating-detail]]
|
|
given an organization's [[risk#Risk Tolerance]].
|
|
|
|
## EVPI Takeoff
|
|
|
|
%%
|
|
## Scratch
|
|
|
|
Expected value of perfect information (EVPI)
|
|
|
|
Count-based takeoff speed increases with count.
|
|
%%
|
|
|
|
Optimizing the takeoff process means:
|
|
|
|
* *Minimizing* the need for information outside of drawings
|
|
* *Maximizing* organizational consistency
|
|
|
|
> [!note]
|
|
> Recent events have complicated my philosophy above.
|
|
> It appears that similar efforts have already been made here,
|
|
> their success being a matter of perspective.
|
|
|
|
> [!note] Naming Conventions (Use Case vs. Description)
|
|
> Naming by use case is intuitive for those without estimating or field experience,
|
|
> but has the side effect that those accustomed to the names will inevitably *treat them as descriptive*.
|